WORKDAY Function in Excel

Question

What is the WORKDAY function in Excel?

Answer

The WORKDAY function can be used to calculate the end date or start date of a project for a given number of business days. The number of business days cannot include weekend days. Specific holidays can also be omitted.  
The syntax for the WORKDAY function is: = WORKDAY ( Start_date, Days, Holidays )

  • Start_date - the start date of the project or time period in question.
  • Days - the number of days work on the project occurred after the Start_date.
  • Holidays - can be used to exclude one or more dates from the total number of working days (optional).  

For more information about Formulas and Functions in Excel, please view the full tutorial from the CTL here: Excel Part 3

If you need further assistance, please click the CTL Support Request button on this page

CTL Support Request

Details

Article ID: 7942
Created
Thu 12/29/22 1:33 PM
Modified
Fri 11/3/23 3:59 PM
KCS Article Status
WIP: Only Problem & some Environment captured
Not Validated: Complete & Resolution captured, confidence lacks in structure, content, no feedback
Validated: Complete & reusable, used by licensed KCS user, confidence in resolution & std. compliance
Validated

Related Services / Offerings (1)

The Center for Teaching & Learning develops and supports a diverse and inclusive community dedicated to excellent teaching, learning, and student educational experience regardless of location, formality, or modality.