Direct vs. Indirect (F&A) Costs

Summary

Direct costs are expenses that can be specifically identified with and assigned to a sponsored project, while indirect (F&A) costs support sponsored projects but cannot be readily assigned to a specific project. Both types of costs must comply with sponsor requirements, applicable regulations, and USD policies.

Body

Question

What is the difference between direct and indirect (F&A) costs on sponsored projects?

Answer

Costs on sponsored projects are generally classified as either direct costs or indirect costs, also called Facilities and Administrative (F&A) costs.

Direct Costs
Direct costs are expenses that can be specifically identified with and assigned to a particular sponsored project. Examples may include:

  • Salaries and wages for employees working on the project

  • Project-specific supplies and materials

  • Travel related to the project

  • Equipment purchased for the project

  • Participant support costs, when allowable

  • Other costs that directly benefit and can be specifically identified with the project

A direct cost must be allowable, allocable, and reasonable, and must comply with the terms and conditions of the sponsored award and USD policies.

Indirect (F&A) Costs
Indirect costs are costs incurred to support sponsored projects but that cannot be readily and specifically identified with a particular project. These costs are also referred to as Facilities and Administrative (F&A) costs.

F&A costs may include expenses related to:

  • Facilities and building operations

  • Utilities

  • Administrative support

  • Accounting and financial services

  • Sponsored program administration

  • Other institutional infrastructure that supports sponsored research and activities

F&A costs are generally recovered through an approved F&A rate applied to the appropriate direct cost base. The applicable F&A rate and cost base are determined by the sponsored award, USD's negotiated rate agreement, and sponsor requirements.

A cost should not be charged directly to a sponsored project simply because funding is available. The cost must meet the requirements for direct charging and be appropriately supported by the project.

Need More Help?

If you need further assistance, please contact GrantsAccounting@usd.edu

 

 

Details

Details

Article ID: 10518
Created
Tue 9/22/26 9:15 PM
Modified
Fri 10/9/26 12:09 PM
KCS Article Status
WIP: Only Problem & some Environment captured
Not Validated: Complete & Resolution captured, confidence lacks in structure, content, no feedback
Validated: Complete & reusable, used by licensed KCS user, confidence in resolution & std. compliance
Validated

Attachments

;